The project has a budget of €442,591 and an estimated completion period of five months

Benidorm City Council, through its Department of Water Services, will begin work next Monday, 16 November, to renew the sewerage and drinking water networks along Calle Júpiter. The project will be carried out in two phases. The first will cover the section between Calle Almendros and Calle Maravall, while the second will extend along the section between Calle Almendros and Calle Tomás Ortuño.

The project has a budget of €442,591.09, which will be funded through the investment funds of Veolia, the company holding the concession for the city's municipal water services. Veolia will also be responsible for carrying out the work. The estimated completion period is five months, “so we hope the work will be finished before Easter”, said Councillor for Water Services José Ramón González de Zárate.

The councillor explained that the reason for the works is that Calle Júpiter “does not have a dedicated drainage network to collect rainwater along its entire length. As a result, rainwater flows towards both ends of the street, at its junctions with Calle Tomás Ortuño, Calle Almendros and Calle Maravall, where it is collected by the existing street drains”.

In addition, the sewerage network along the section between Calle Tomás Ortuño and Calle Almendros “is more than 50 years old and in a considerably deteriorated condition, resulting in frequent blockages and the risk of wastewater overflowing onto the street”.

For these reasons, González de Zárate stated that “the drinking water supply and sewerage networks along Calle Júpiter need to be renewed between Calle Tomás Ortuño and Calle Almendros. A new rainwater drainage network must also be installed along the section between Calle Maravall and Calle Tomás Ortuño”.

The proposed solution will allow the rainwater downpipes from buildings to be connected to the new network, provide new street drains along the road and improve the overall performance of the municipal water infrastructure. It will also enhance the quality of water supply, sewerage and drainage services in this area.

Once the underground works have been completed, the project will include reinstating the affected road surface. To this end, the current layout of Calle Júpiter will be modified by introducing a shared-level street, with pavements and carriageway at the same height, “as is already the case on most streets in this part of the city”, González de Zárate pointed out.

The new layout will feature paved pedestrian areas and an imprinted asphalt road surface.

The project will also include the extension of the fire hydrant network and the replacement of 231 metres of stormwater and wastewater pipelines.

Once the works have been completed, new trees will be planted, together with a new irrigation system, benches, bollards and planters. The aim is to “create a new pedestrian-priority public space for residents”, the councillor said.

González de Zárate also pointed out that this is an area “with a very busy shopping street and a health centre that is extremely important for Benidorm”. He also asked local residents “to be a little patient, as these works are much-needed improvements for the neighbourhood”.

The works will have very little impact on local traffic, as the only road closure will affect Calle Júpiter along its entire length, from Calle Maravall to Calle Tomás Ortuño. No traffic diversions will be necessary. Residents will also be allowed access to their driveways and garages, depending on the progress of the works.
 

José Ramón González de Zárate Corte 1
José Ramón González de Zárate Corte 2
José Ramón González de Zárate Corte 3