Over the next 10 days provisionally will be enabled the baths of one of the dressing rooms
The Sports Council has launched this week the expansion works of the bathrooms of the football Antonio López, in the Rincón de Loix, as the current is insufficient to serve all users and viewers of these facilities, especially weekends. The works, which have a budget of 17,600 euros plus VAT and a lead time of about 20 days, provide restructure existing bathrooms and create three new ones. To do so is to retrain as part of the existing warehouse bathrooms. For about 10 days, the current bathrooms and barber become unusable, as they have to be demolished to make pipes of the new toilets. In this period will continue to run the toilets for the disabled and enabled for general use the nearest locker room, number 1. After completion of the works, the exhibition will feature three bathrooms with three cabins and three sinks for women ; two bath cabin knights and three urinals; plus a bathroom for the disabled.