Benidorm launches tendering for the third and final phase of the Levante Beach overhead power line project
The section to be refurbished runs from Filipinas Avenue to the end of Madrid Avenue, with a tender budget of €2,378,176.59 and a completion period of five months
The project will reduce installed power capacity by 37.86%, helping to lower emissions while improving energy efficiency and sustainability
Benidorm Town Council’s Local Government Board has today approved the launch of the tendering process for the third and final phase of the renovation of the Levante Beach overhead electrical system. The section concerned runs from Avenida Filipinas to the end of Avenida de Madrid, completing the refurbishment of the entire Levante Promenade.
According to the tender documents, the estimated contract value is €2,378,176.59, with a completion period of five months. In addition to improving the safety, reliability and maintenance of the public lighting and overhead power line, as well as their overall appearance, the project will also significantly increase energy efficiency.
According to estimates drawn up by the technical team, upgrading the system will reduce the total installed power capacity along the section covered by the project by 37.86%. As Mayor Toni Pérez explained. “This will also help us reduce emissions and become more sustainable and more efficient in our management”.
The tender evaluation process includes a mathematical criterion worth up to 60 points, under which bidders may submit the price reduction they consider most appropriate in light of current market supply and demand conditions.
A further 40 points will be awarded for technical criteria. These are intended to ensure bidders thoroughly assess and understand the actual scope of the works before submitting their proposals, helping prevent speculative bids submitted simply to secure the contract without first gaining a proper understanding of the project’s requirements.
Once this project is complete, Benidorm Town Council will have upgraded the public lighting and overhead electrical installations along the Levante Promenade. The renovation programme began in 2022 in response to the need to modernise infrastructure that was more than three decades old, had deteriorated over time and had not kept pace with the latest, more modern and energy-efficient technologies.
As a reminder, the first phase of the project was carried out between late 2022 and the first half of 2023, covering the section from Plaza del Torrejó to Avenida de Europa. The Town Council invested €1,972,119.41 in the works, funded entirely through municipal resources.
The second phase, which has also been completed, covered the section between Avenida de Europa and Calle Metge Miguel Martorell. It had a budget of €854,885.07 and was funded by European funds through the ‘Benidorm Vision 360’ Sustainable Tourism Destination Plan.
Finally, Toni Pérez once again pointed out that “as has been the case with many other infrastructure projects, this is work that should be funded and carried out by the national government. However, faced with yet another failure to meet its responsibilities, Benidorm Town Council will take on the project and carry it out because we believe this is what Benidorm deserves”.
The Mayor criticised the fact that “while the central government carries out and rebuilds infrastructure in many other municipalities, it continually turns a blind eye to Benidorm, and we have plenty of examples”. Among these, he cited “the first two phases of the overhead electrical system itself and the access roads to the tertiary sector, where we have been forced to build a roundabout on a national road”.