THE WEATHER IN BENIDORM NOW

29

15:43 PM

TIME IN BENIDORM

18ºC

Cloudy

SW 35km/h

WIND DIRECTION AND SPEED

5%

CHANCE OF SHOWERS

SELECT A PORTAL

CITIZEN

Information to live in the city

COMMUNICATION

Press, Radio and TV

FILM OFFICE

Office of filming

SMART CITY

Indicators of our destination

EUROPEAN FUNDS

Actions co-financed by the EU

CHOOSE YOUR PREFERENCES

SELECT A LANGUAGE FOR THIS COMPUTER OR DEVICE

Current size: 100%

ADJUST THE FONT SIZE
ADJUST THE CONTRAST SIZE

The works that will complete El Murtal II with green zones of games and endowments start

13 January 2017
Comienzan las obras que completarán el Murtal II con zonas verdes, de juegos y dotacionales

The urbanization, by the Compensation Board of the plan, will be completed before six months and will allow the opening of Moralet Avenue and half of Guatemala Avenue

The works that will complete the urbanization of the Murtal II sector, which has been undergoing for years, have already begun, after last September the Government Council Benidorm City Hall approved the project of timely modification of the Partial Plan. This urbanization will generate space for educational, sports and recreational use, and children's games, as recalled the mayor, Toni Pérez, who has visited the sector together with the councilwoman of Urbanism, Lourdes Caselles, to see the progress of the works.

Pérez recalled that the Partial Plan Murtal II affects the soil between Colombia Avenue and the future Guatemala Avenue; that is, in the immediate vicinity of the In Tempo building and the Sunset Drive complex being built by the TM group.

The urbanization of the sector is the responsibility of the Compensation Board - former figure of the developer agent - is valued at 1.9 million euros, and will finish in less than six months.

With this urbanization almost 15,000 square meters of public gardens with trees and lawns will be created and a play area of ​​4,000 square meters, a portion of educational use of just over 8,700 meters and a sports park of more than 7,000 square meters . In addition, the City Hall will receive a plot of 4,000 square meters, which corresponds to 10% of the use of the sector.

The mayor stressed that the urbanization "will allow opening Moralet Avenue - already under construction - and half of Guatemala Avenue, until the link with the sector PP 2/1." In fact, it is up to the developers of the latter to run the other half of the avenue. Likewise, he has insisted that the development of this sector gives continuity to the urban fabric and generates streets, garden zones and public endowments in a hitherto unused space.

Sunset Drive Resort

The councilwoman responsible for Urban Planning, municipal specialists and representatives of the Compensation Board has moved to the urbanization of El Murtal II after visiting two show flats of Sunset Drive, the residential complex divided into two towers and with more than 13,000 meters Squares of common areas and recreation that the TM promoter is executing within the sector.